P&A Consulting Engineers, PLLC was retained to retro-commission a well-known Hotel in NYC that had been dormant for almost 2 years due to Covid. Ownership requested a condition assessment and deferred maintenance plan in order to re-open the facility. All MEP systems were reviewed including:
- Chiller Plant
- Electrical infrastructure
- Fire Alarm System
- Plumbing Infrastructure
- Heating Plant
- Emergency Generators
An Action Plan was developed which focused on Life Safety and Operational Capability of the systems. Further development of Commissioning Specifications and On-site testing was provided to assure proper re-opening and operation of the facility.